How projects, work items and EVM fit together

VNCproject organises delivery in three layers.

Projects, work items and time and plans roll up into earned value

  1. Projects — a container with a key (for example apollo), a status and an EVM mode (money or none).
  2. Work items — the units of work inside a project, each with a subject, status, priority, assignee, Done % and due date.
  3. Time and plans — time entries and plan dates that feed progress and capacity.

When a project’s EVM mode is money, the project tracks earned value: progress Done % combines with budget and actual cost to give the metrics you see in the view (for example the project’s EVM flag on the portfolio table). Projects with EVM = none simply track progress without money.

The maths is deterministic and runs on the server, so the portfolio roll-up and the project views agree.

My capacity compares your allocations (percent, over a date range) with availability for the next weeks. Allocating a person more than 100% lights the heat-map, which is how over-commitment is spotted early.

Work items are the reliable unit (a status and a percent each); projects roll them up; capacity looks across projects for the same people. Keeping them separate is what lets the same work item appear on a board, a plan and a report without a second copy.

Applies to VNClagoon 2026.09 and later. Last reviewed on 26 September 2026.